Survey and installation page
In this section is a complete manual for surveying, measuring and
installing PVCu replacement windows. Use this information as guidance
only. If any doubts or unique installations seek professional help.
For specific help that we can give guidance on, email us at diy@lowcostwindows.com.
Contents
Surveying
General information
Good surveying is the basis of ensuring a quality installation.
Follow these points:
- Is the chosen window satiable for the opening, window swing etc.
- Is the surrounding masonry and structure in good order, if not
investigate and rectify the defect before proceeding.
- which method of fixing will be suitable for the opening.
Through fixing
The most common method and causes less damage to internal finishes.
Fixing it directly through the PVCu frame.
Lug fixing
This method is used in situations where fixing is not possible. We
recommend you seek advice in this situation.
The presence of any electrical or specialist items such as television
aerials and telephone wires or curtain tracks should be noted. Wherever
possible such services should be routed around, and not through, the
frames of plastic windows. Where this is not possible guidance should
be sought.
Load bearing
It must be assumed that all bay window assemblies are load bearing,
unless it can be determined by a qualified person that adequate alternative
support is provided for all dead and imposed loads. An example would
be a mullion bay window.
^Top
Measurement
General information
If the preliminary survey is satisfactory proceed to the measuring
of the opening.
|
Width
Measurements of the width of the structural opening at the
top,middle and bottom of the window are taken. The smallest
of these measurements are taken as the window width.
Height
Similarly three measurements are taken at both ends and the
middle of the opening. Again the smallest is used as the window
height.
|
 |
It is good practice to deduct 10 to 12 mm from the minimum size of
both width and height when measuring. This ensures a sufficient gap
between frame and opening for installation.
In some occasions, usually due to subsidence. The opening can skew.
It is good practice when measuring to measure both diagonals. Ensure
that both measurements are equal to within 10 mm of each other. If
not please seek guidance.
Note: When building work is being undertaken to house the window,
do not build around the window in situ. But wait until the last possible
moment before installing.
^Top
Installation
Windows shall be installed plumb and square without twist, racking
or distortion of the window to within stated tolerance. To ensure
correct operation after installation.
Pvcu window frames are manufactured accurately to specified outer
frame dimensions and have specific opening light to fixed frame cleaners
for operational efficiency. Distortion of any frame or sash member
will reduce the performance, impair the operation and create a security
risk.
Window positioning
Positioning of your windows is done on the back of your judgment.
These factors must be taken into account when positioning:
- Bridge the cavity.
- Cover the Damp Proof Course (D.P.C.).
- Set back as far as possible.
When a thinner window frame replaces the original thicker one, it
is customary to fit back to the existing plaster and make good externally.
In cases where the new frame is much thicker, i.e. replacing steel
frames, it may be necessary to remove plaster to ensure that the outside
face of the new frame is fitted inwards of the building line.
^Top
Fixings
All metal fixings such as lugs, screws and bolts should be of materials
and finishes intended to offer the best corrosion resistance for the
situation. They should therefore be made from one of the following:
- Stainless steel grade A2, A4 or F1 complying with BS 6105.
- Steel which has been finished by one of the following methods:
- Zinc plating in accordance with classifications No. Zn3 of
BS 1706 and chromate passivation in accordance with class 2C
or 2D of BS 6338.
- Hot dip galvanising in accordance with BS 729 to a minimum
coating mass of 460g/m2
- Spraying with a zinc coating in accordance with symbol Zn4
of BS 2569: Part 1
- Sheradizing in accordance with class 2 of BS 4921
- Aluminum alloy 6063 TF, 6063 TE or 6063 TB complying with BS 1474
anodized to grade aa15 of BS 1615
Where it is necessary to blend fixing lugs to suit the perimeter
gap, this should done before the lugs are fitted to the frame, otherwise
the bending operation may distort or damage the frame.
^Top
Preferred methods of
fixing
Fixing methods should take into account thermal movement and will
be influenced by:
- Presence or absence of wall cavity.
- Type of cavity - open or closed.
- Relative position of the frame with regard to the cavity.
- Plaster line and any requirement to preserve interior decoration.
- The design of the reveal.
There are two principle methods of fixing available, which may be
used either separately or in combination they are:
- Through frame fixing.
- Lug fixing.
Foam fixing offers a useful supplementary method of fixing where
through frame or lug fixing prove impractical (for example at aperture
heads). The technique requires skilled application to avoid problems
of the frame distorting. Be sure to read and follow the manufactures
instruction on using the foam.
^Top
Preferred fixing distances
|
The distance between adjacent fixings is chosen after careful
consideration of all relevant factors. These are:
- Position of transoms and mullions.
- Position of hardware.
- Nature of the adjacent structural materials.
In general, all four sides of the frame should be secured using
the following guidelines to determine fixing spacing:
- The corner fixings shall be a minimum of 150mm and a maximum
of 250mm from the corner.
- No fixing shall be closer than 150mm to a transome or mullion
center line.
- Intermediate fixings shall be at centers no greater than
600mm.
Finishing off
Every care should be taken during installation to ensure
that debris such as wet plaster, etc., does not foul drainage
holes or impair the operation of the hardware.
Internal revals should be made good, ready for redecoration.
When making good internally, the materials used should not be
applied on top of existing wall covering materials, as the former
would be removed during redecoration. Neither sand and cement
or plaster should be used to fill the gap between the the back
of the frame and the structural opening.
When it is necessary to seal internally, such sealants should
be capable of accepting paint or wallpaper.
|
  |
^Top
Sealing the structure
When external sealing with mastics is used, an amine or neutral
cured silicone of polyurethane sealant which complies with type A
of BS 5889 is to be used. If unsure seek guidance.
When external gaps exceed 6mm, the requirements of good joint design
call for the use of a suitable back up material to provide bedding
for the sealant. Suitable types are either foamed, compressible or
expandable performed strips, or 'in situ' expanding foam.
No seal joint should exceed 15mm in width and those wider than this
should be reduced to acceptable dimensions for sealing through the
use of pvcu pieces.
No seal joints should be less than 5mm
^Top
Glazing
General
All glazing must comply with requirements of BS 6262, in addition
recommendation from glass and glass unit manufacturers should be followed.
All glass and insulated units should be examined carefully for damage,
especially at the edges, prior to installation. Defective Items should
not be used. The size of the glass used for glazing must be such that
both the necessary clearance between the edge of the glass and the
base of the rebate, and also the necessary sealing joint gaps are
present.
Recommendations for Glazing Procedure
The system designers recommendations should be followed.
Glazing gaskets, especially pressure wedges are prone to creep back
which can result in unacceptable gaps at critical junctions. This
can turn significantly and impair the performance of a window.
All possible precautions must be taken and it is suggested that the
following guidelines be considered:
- All gaskets should, where possible, go around a window in one
piece. The joint will be in the least exposed area of the window
(in most cases this will be in top center) and all seal junctions
will be offset.
- Pressure seals are the most sensitive gaskets to creep back. If
they are not designed to prevent over-stretching, the following
procedure should be adopted in addition to the guidelines stated
in the above paragraph.
- It is advisable that gaskets should be cut oversized, so they
are not extended under tension when assembled. The excess material
will provide loops along the edges of the window which will be pushed
into position only after the seal joint faces and corners are secure.
- If it is not possible to fit the pressure gasket as a continuous
piece, each section must be over cut and installed as already stated
in the above paragraph.
- ^Top
Glazing blocks
The use of glazing blocks is essential to allow the windows to function
correctly. The manufacturers recommendation or block sizes, material
and locations should be followed exactly. This is particularly important
for side hung and tilt and turn windows.
Securing the glass
The glass or glazing is usually secured in place with glazing beads
incorporating glazing gasket.
In certain circumstances it may be advisable to use sealing tapes
or resilient sealants to severe the glass or glazing units, or to
supplement the use of glazing beads. When these methods are used,
the recommendation of the sealing tape or sealant manufacturers must
be followed with regard to their use.
Drainage
It is essential that the systems suppliers recommendations for securing
the glass in place are followed. Specifically, care must be taken
to ensure that glazing blocks or spacers do not obstruct drainage
of the water from the glazing rebate.

^Top
Final checking
The purpose of the final checks is to ensure that the installation
is of a high standard. It is advisable that, in the absence of any
formal handover procedure, these checks are carried out in the presence
of the customer. They should be that:
- All glazing beads and gaskets or glazing sealant are adequately
fitted.
- All opening lights function correctly and are fitted square within
the frame.
- All locking points engage in their respective keeps.
- No gaps exist between frames and weather-strips.
- All swarf and debris has been removed from channels and drainage
paths.
- There is no movement in the outer frame.
- There are no cracks or breaks in any frame member.
^Top
Cleaning and maintenance
General
In general the maintenance of uPVC windows requires only that
they are washed, and that the systems suppliers instructions should
be followed if any periodic lubrication of mechanism is required.
uPVC is particularly resistant to both marine and industrially polluted
environments. Certain solvents, e.g.. Ketones and chlorinated hydrocarbons
will affect the surface of the uPVC. Ruct stains cannot be removed
by normal methods.
Cleaning
uPVC windows should be cleaned at periodic intervals to maintain
their original appearance. The frequency depends upon the ambient
atmosphere but as a general rule the frames should be cleaned whenever
the glass is cleaned.
The best method of cleaning is to use a clean cloth and a solution
of detergent, diluted to the normal concentration for washing-up.
It is important to 'flood' the uPVC frame, and at no time rub the
dirt with a dry or semi-dry cloth, as this might lead to micro-scratching
of the surface.
Internal surfaces may be polished with a colourless silicone furniture
polish after washing if required.
Special
circumstances
If a surface has been allowed to become excessively dirty, it
should be cleaned as recommended above. If any unsightly stains remain,
they should be removed using a mild household non-scouring cream,
followed by washing.
Abrasive materials should not be used for any cleaning purposes as
these can cause micro-scratching of the surface. Especially avoid
the use of steel wool pads, as they might cause permanent stains.
^Top
|